You are here: Home / Common Installation Mistakes & Corresponding Solutions for Vertical Turbine Pumps

Common Installation Mistakes & Corresponding Solutions for Vertical Turbine Pumps

Vertical turbine pumps are widely used in water supply, irrigation, and industrial water extraction due to their high lift and efficiency. However, improper installation often leads to reduced performance, increased energy consumption, or even equipment failure. Below are the 8 most frequent installation mistakes and their professional solutions, along with preventive tips.
1. Incorrect Alignment of Pump Shaft & Motor Shaft
Mistake Description

Misalignment (parallel misalignment, angular misalignment, or combined misalignment) between the vertical turbine pump’s drive shaft and the motor shaft is one of the most common issues. This causes uneven stress on bearings, seals, and shafts, leading to abnormal noise, rapid wear, and shortened component lifespan.

Root Causes
1. Rushing the alignment process without using professional tools.
2. Ignoring base deformation (e.g., uneven concrete pouring or base settlement) that shifts the motor/pump position.
3. Reusing old or damaged coupling components (e.g., worn flexible couplings) that cannot compensate for minor misalignment.
Solution
1. Use Precision Alignment Tools: 
Employ laser alignment tools (preferred) or dial indicators to measure alignment. For vertical shafts, ensure the radial runout of the coupling is ≤0.05 mm and the axial runout is ≤0.03 mm.

2. Level the Base First: 
Before installing the pump/motor, verify the base flatness with a spirit level (error ≤0.1 mm/m). If the base is uneven, use stainless steel shims to adjust until level.

3. Replace Worn Couplings: 
Install new, high-quality flexible couplings (e.g., rubber or jaw-type) that match the pump’s torque rating to absorb minor alignment deviations.
2. Improper Submergence Depth of the Impeller
Mistake Description

The impeller of a vertical turbine pump must be submerged in the fluid (e.g., water) to avoid vortex formation (air entrainment) or dry running. Insufficient submergence causes cavitation, reduced flow/lift, and impeller erosion; excessive submergence increases hydraulic resistance and energy waste.

Root Causes
1. Miscalculating the minimum submergence depth (MSD) required for the pump model.
2. Ignoring changes in the fluid level (e.g., seasonal water level drops in wells or tanks) during installation.
Solution
1. Refer to Manufacturer’s Specifications: 
The MSD is typically 1.5–3 times the impeller diameter (e.g., a 100 mm impeller requires ≥150 mm submergence). Check the pump’s technical manual for exact values.

2. Adjust the Pump’s Vertical Position: 
For fixed-base installations, use adjustable support brackets to lower/raise the pump until the impeller is submerged to the required depth. For well pumps, ensure the pump intake is at least 0.5 m above the well bottom to avoid sediment suction.
3. Poor Pipe Connection & Leakage
Mistake Description

Leakage at the suction/discharge pipe connections (e.g., flange joints, threaded connections) or improper pipe routing causes:

1. Air entry into the suction pipe (leading to cavitation and flow loss).
2. Reduced discharge pressure (due to fluid leakage).
3. Vibration (from uneven fluid flow in misaligned pipes).

Root Causes
1. Using mismatched pipe sizes (e.g., a smaller discharge pipe than the pump’s outlet flange).
2. Skipping gaskets or using low-quality gaskets (e.g., rubber gaskets not resistant to the fluid’s temperature/pH).
3. Over-tightening or under-tightening flange bolts (over-tightening damages gaskets; under-tightening causes leaks).
Solution
1. Match Pipe Sizes to Pump Ports: 
Ensure the suction/discharge pipes have the same inner diameter as the pump’s inlet/outlet flanges (never reduce the suction pipe diameter—this increases flow resistance).

2. Use Suitable Sealing Materials: 
Select gaskets compatible with the fluid (e.g., EPDM gaskets for water, PTFE gaskets for corrosive fluids) and replace old/damaged gaskets.

3. Torque Flange Bolts Evenly: 
Use a torque wrench to tighten bolts in a crisscross pattern (e.g., 1-3-2-4 for 4-bolt flanges) to the torque value specified in the pump manual (typically 25–50 N·m for standard flanges).
4. Neglecting Well/Suction Tank Preparation (for Well/Tank Installations)
Mistake Description

For vertical turbine pumps used in wells or tanks, failing to clean the well/tank or verify its structure leads to:
1. Sediment accumulation in the impeller (causing imbalance and wear).
2. Blockage of the pump’s suction screen (reducing flow).
3. Damage to the pump shaft from debris (e.g., rocks, rust flakes).

Root Causes
1. Skipping well development (e.g., flushing sediment from the wellbore) before installation.
2. Not installing a suction screen (or using a screen with oversized openings) to prevent debris entry.
Solution
1. Clean the Well/Tank Thoroughly:
(1) For wells: Flush the well with high-pressure water until the discharged water is clear (no sediment). Use a well brush to remove rust or scale from the wellbore.

2. For tanks: 
Drain and scrub the tank interior to remove sludge, algae, or foreign objects.
(1) Install a High-Quality Suction Screen: Mount a stainless steel screen (mesh size ≤1 mm) at the pump’s suction intake to block debris. Ensure the screen has sufficient open area (≥2 times the suction pipe area) to avoid flow restriction.
5. Incorrect Grouting of the Pump Base
Mistake Description

Grouting fills the gap between the pump base and the concrete foundation, providing stability and reducing vibration. Poor grouting (e.g., incomplete filling, using low-strength grout) causes:
1. Pump base movement (leading to shaft misalignment over time).
2. Amplified vibration (transmitted to the foundation and adjacent equipment).
3. Cracks in the pump base or foundation.

Root Causes
1. Using ordinary concrete instead of high-strength, non-shrinking grout (concrete shrinks as it cures, leaving gaps).
2. Pouring grout too quickly (trapping air bubbles) or not vibrating it to ensure full contact with the base.
Solution
1. Select the Right Grout: 
Use non-shrinking, high-compressive-strength grout (e.g., epoxy-based or cementitious grout with ≥60 MPa compressive strength) suitable for vertical turbine pumps.

2. Follow Grouting Best Practices:
(1) Clean the foundation and pump base to remove oil, dust, or loose material.
(2) Pour grout slowly from one side to avoid air entrapment; use a vibrator to compact the grout.
(3) Allow the grout to cure fully (per manufacturer’s instructions, typically 7–14 days) before tightening base bolts or starting the pump.
6. Improper Bearing Lubrication
Mistake Description

Vertical turbine pumps rely on bearings (e.g., ball bearings, sleeve bearings) to support the rotating shaft. Over-lubrication, under-lubrication, or using the wrong lubricant causes:
1. Bearing overheating (due to increased friction from under-lubrication or viscous drag from over-lubrication).
2. Bearing seizure (in severe cases, leading to shaft bending).
3. Contamination (if lubricant is not compatible with the fluid or environment).

Root Causes
1. Guessing the lubricant type/amount instead of following the manual.
2. Reusing old lubricant or mixing different lubricant grades.
Solution
1. Use the Specified Lubricant: 
Refer to the pump manual for lubricant type (e.g., lithium-based grease for water pumps, synthetic oil for high-temperature applications) and viscosity grade.

2. Apply the Correct Amount:
(1) For grease-lubricated bearings: Fill 1/3 to 1/2 of the bearing housing (over-filling causes overheating).
(2) For oil-lubricated bearings: Maintain the oil level at the centerline of the lowest rolling element (check with the oil sight glass).

3. Replace Lubricant Before Start-Up: 
Even if the pump is pre-lubricated at the factory, replace the lubricant if it has been stored for more than 6 months (to avoid degradation).
7. Skipping Pre-Start-Up Checks
Mistake Description

Starting the pump without verifying key conditions leads to immediate damage (e.g., dry running, motor overload). Common skipped checks include:
1. Not priming the pump (for non-self-priming models).
2. Ignoring blocked suction/discharge valves.
3. Failing to test motor rotation direction.

Root Causes
1. Rushing to commission the pump to meet deadlines.
2. Lack of training for on-site installers (unaware of pre-start protocols).
Solution
1. Prime the Pump (If Required): 
For non-self-priming vertical turbine pumps, fill the suction pipe and pump casing with fluid until all air is purged (use the priming port if available).

2. Verify Valve Positions: 
Open the suction valve fully and partially open the discharge valve (1/4 to 1/2 open) to reduce start-up pressure (close the discharge valve only for centrifugal pumps with low power ratings—follow the manual).

3. Check Motor Rotation:
(1) Disconnect the pump coupling from the motor.
(2) Start the motor briefly (≤5 seconds) and confirm the rotation direction matches the arrow on the pump casing (reverse rotation causes no flow and impeller damage).
(3) Reconnect the coupling only if rotation is correct.
8. Inadequate Vibration & Noise Monitoring During Installation
Mistake Description

Vibration and noise are early warning signs of installation errors (e.g., misalignment, imbalance). Ignoring them during commissioning allows small issues to escalate into major failures (e.g., shaft breakage, seal leakage).

Root Causes
1. Not using vibration meters to measure baseline vibration levels.
2. Dismissing “minor” noise as “normal” pump operation.
Solution
1. Measure Baseline Vibration: 
Use a portable vibration meter to test vibration at the pump base, motor housing, and bearing caps. The acceptable vibration velocity for vertical turbine pumps is typically ≤2.8 mm/s (RMS) at rated speed.

2. Troubleshoot Abnormal Vibration/Noise:
(1) If vibration is high at the coupling: Recheck shaft alignment.
(2) If noise is a “gurgling” sound: Inspect for air entry in the suction pipe (leaks or insufficient submergence).
(3) If vibration increases with load: Check for impeller imbalance (e.g., sediment buildup) or pipe resonance (add pipe supports to reduce vibration).
Key Preventive Tip: Follow the Manufacturer’s Installation Manual

Every vertical turbine pump model has unique requirements (e.g., alignment tolerances, lubricant types, submergence depths). Always refer to the original equipment manufacturer (OEM) manual as the primary guide—never rely solely on general installation. Additionally, train on-site installers to use professional tools (laser aligners, torque wrenches) and document each installation step for future maintenance.
By avoiding these common mistakes and implementing the solutions above, you can ensure the vertical turbine pump operates efficiently, reliably, and with a long service life.