You are here: Home / Service&Support / Cases / Vertical Turbine Pump for High-Altitude Copper Mine Dewatering in Chile

Vertical Turbine Pump for High-Altitude Copper Mine Dewatering in Chile

Views: 0    

A large underground copper mine in an arid part of Chile needed continuous dewatering at 2,300 m above sea level. The installation had to clear standing water from galleries, manage seepage and route wastewater from the on-site foundry. These duties supported underground pressure relief, helped keep access routes clear and allowed mining and processing to continue.

The existing pumps suffered from severe corrosion, erratic discharge, and frequent breakdowns. The drive also struggled to deliver adequate power at elevation. With little downtime available for pump maintenance, the mine needed a replacement capable of sustained high-load operation.

Pump Model and Stainless Steel Lineshaft Configuration

To eliminate corrosion and flow instability, the pump selection focused on two critical design factors: corrosion-resistant wetted components and a heavy-duty underground shaft configuration. WY PUMPS chose an all-304 stainless steel vertical turbine pump for the combined mine water and foundry wastewater stream. The enclosed lineshaft was designed to limit transmission losses and maintain steady power transfer along the pump column under load. It also addressed the need for stable transmission in a deep installation, where vibration or irregular delivery would complicate continuous operation.

The Siemens motor was matched to the site supply and the pump’s speed and output requirements. Motor sizing accounted for high-altitude thermal derating at 2,300 meters, and load testing was integrated directly into the site commissioning protocol.

Parameter

Supplied equipment

Pump model

350LJC370-16×4-90KW

Specified flow and head

270 m³/h at 73 m

Motor and speed

Siemens 90 kW, 440 V, 1,450 r/min

Pump construction

All 304 stainless steel with an enclosed lineshaft

Specified installation dimension

5,400 mm

Customer Requirements

The replacement pump had to handle a mixture of mine water and foundry wastewater containing trace mineral dust, dissolved metal ions and fine solids. Corrosion and scale buildup could shorten the service life of conventional cast-iron pumps and eventually lead to leaks. The mine therefore needed a pump that could resist corrosion and wear and be serviced within short maintenance windows.

At high altitude, thinner air reduces motor cooling. The motor had to deliver enough power for continuous dewatering without overheating, overloading or tripping unexpectedly.

Delivery and Underground Pump Commissioning

The project took 100 working days from fabrication through commissioning and operator training. Custom stainless steel fabrication, precision machining, assembly, and factory inspection were completed in the first 40 working days, while sea freight, underground installation, on-site testing, and operator training spanned the remaining 60 days.

At the mine, the installation team positioned the pump underground, aligned the lineshaft and adjusted the drive before running water through the system. The wet trial then tested the assembled pump under load at the mine’s operating elevation.

Project Results and Customer Feedback

The pump met the commissioning requirements on its first wet trial and entered routine dewatering service. It maintained steady flow while draining underground galleries and transferring foundry wastewater. The enclosed lineshaft ran without noticeable vibration or abnormal noise.

In service, the stainless steel pump showed no visible rust, scaling or blockages. The Siemens motor maintained adequate cooling and ran without overload faults during continuous high-load operation at altitude. The mine selected the model for long-term procurement based on its suitability for the site, stable operation and low operating and maintenance costs.

Sizing a vertical turbine pump for underground mine dewatering requires evaluating hydraulic duty, fluid characteristics, and shaft spatial constraints. Include the following details in an inquiry to WY PUMPS:

  • Duty and site conditions — design flow, total head, site elevation and operating schedule

  • Water characteristics — water chemistry, solids content and particle size, if known

  • Installation and power — shaft or sump dimensions, access for servicing and available supply voltage

Request Mine Dewatering Pump Selection

Planning an underground mine dewatering system? Share your site elevation, water composition and solids content, design flow and head, installation dimensions, and available power supply. WY PUMPS can help select the pump materials, lineshaft arrangement, and motor for the duty.

Telephone/WhatsApp

+8613912908767

WeChat

17327729166

Quick Links

Product Category

Contact Us

Leave a Message
Copyright © 2025 Nanjing Wangyang Pumps Co., Ltd . All Rights Reserved.| Sitemap| Privacy Policy