A high-rise development in the Le Van Luong area of Vietnam combines commercial and residential space. The project required a dedicated fire protection water supply as part of the building system. The network had to remain ready year-round across the development.

On-time fire protection installation was critical to the overall construction schedule. The local team needed to integrate the pumping equipment with the building network and allow time for commissioning and fire protection acceptance before the development could be handed over.

Vertical Turbine Fire Pump Models and Configuration

Emergency water delivery was handled by two vertical turbine fire pumps supplied by WY Pumps. Since system standby pressure was maintained separately (e.g., via a jockey pump), the main pumps were sized specifically for peak emergency duty.

Pump model

Flow rate (t/h)

Head (m)

350LJC370-16×5-110KW

252

94

450LJC650-32×4-260KW

468

125

Customer Requirements

This operational setup required verifying two key performance criteria: maintaining static pressure during standby, and ensuring the main pumps started promptly, sustained rated emergency flow, and shut down automatically as required. The customer specified NFPA 20 and required the installation to pass the applicable Vietnamese fire protection acceptance process.

Due to the hot and humid environment in the pump room, reliable moisture resistance and electrical insulation were critical. The equipment had to be straightforward to install and service so the local team could complete testing and carry out routine maintenance.

Delivery and Fire Pump Commissioning

Manufacturing, factory testing, and dispatch were completed within 35 working days, followed by a 7-day sea freight transit to Hai Phong. On-site installation, commissioning, and final regulatory sign-off took an additional 10 working days—delivering a complete turnkey timeline of 52 working days. The local distributor handled installation, commissioning and trial operation.

Crated equipment staged outside the Le Van Luong building
Red fire protection pipework in the Le Van Luong pump room
Close view of a red pump assembly and adjoining pipework

Crated equipment at the project site before installation

A wide view of the installed fire protection pipework

A closer view of an installed pump assembly and pipe connections

Project Results and Customer Feedback

The simulated fire-demand test showed that the system could move from stable standby pressure to sustained emergency water delivery with a prompt pump response. Every unit met all commissioning criteria on the first pass. The Vietnamese authorities accepted the installation, allowing the project to meet its fire protection milestone before handover.

The pumps have operated reliably with zero moisture-related issues or mechanical failures. The customer found the equipment straightforward to maintain and expressed interest in a long-term supply relationship.

To receive a tailored pump selection and quote, please share your required flow rate and head, water source and sump depth, installation constraints, power supply specifications, and applicable fire protection standard (e.g., NFPA 20). For buildings with multiple pressure zones, include the required duty for each pump.

Request Fire Pump Selection

Selecting a fire pump for a high-rise building? Send your design fire flow and head, water source and available water levels, pump-room dimensions, and applicable fire protection requirements. WY PUMPS can review the duty and installation conditions with your project team.

Telephone/WhatsApp

+8613912908767

WeChat

17327729166

Quick Links

Product Category

Contact Us

Leave a Message
Copyright © 2025 Nanjing Wangyang Pumps Co., Ltd . All Rights Reserved.| Sitemap| Privacy Policy