Views: 0
A municipal water supply upgrade in Thanh Hoa Province, Vietnam, was implemented to resolve low water pressure and intermittent supply issues during morning and evening peak hours. The pumping station serves residential tap-water delivery, pressure support in the municipal distribution network and day-to-day water allocation. It operates around the clock from an outdoor pump house in a hot, humid tropical climate.
WY PUMPS supplied a high-capacity vertical turbine pump with an IP55 vertical variable-speed motor. The customer reported steadier pressure and more even water delivery after commissioning. The supplied motor ran continuously for two years without a reported fault.
WY PUMPS supplied a high-capacity vertical turbine pump and a matching IP55 vertical variable-speed motor. Engineered specifically for harsh tropical conditions, the pump features robust moisture and corrosion resistance, high heat tolerance, low operating noise, and stable water transfer.
A variable-speed pump for municipal water supply allows output to follow demand. At Thanh Hoa, operators could adjust motor speed to change pump flow and head, increasing output for the morning and evening peaks and reducing it as demand eased. The higher transfer capacity supported the peak load, while the speed adjustment helped maintain distribution pressure as the network load changed. The pump and motor combination was intended for long-term continuous service.
The IP55 motor enclosure ensured reliable protection against moisture and dust in the outdoor pump house. Beyond environmental protection, accurate vertical turbine pump sizing for comparable municipal water projects requires evaluating key hydraulic parameters—including daily flow profiles, total dynamic head (TDH), target network pressure, and specific pump performance curves—to define the optimal operating range.
Parameter | Supplied equipment |
|---|---|
Pump model | 350LJC320-53*1-75KW |
Motor | IP55 vertical variable-speed motor |
Flow rate | 250 t/h |
Head | 60 m |
Urban expansion and a growing residential population pushed demand beyond the transfer capacity of the aging supply equipment. The shortcomings showed up most often at the two busiest times of day. Pressure dropped, some neighborhoods experienced local interruptions, and water delivery varied across the service area. The municipality needed higher transfer capacity and steadier pressure to maintain dependable residential tap-water service.
The customer also emphasized operational familiarity, ensuring that the new system seamlessly integrated with their existing station workflows and maintenance routines. Ease of operation, fewer faults, lower maintenance costs and lower energy use all mattered because the equipment was intended for continuous municipal service. A predictable delivery schedule and prompt installation and commissioning were needed to fit the works programme and limit disruption to households.
Thanh Hoa’s tropical monsoon conditions bring year-round heat and humidity and an extended rainy season. The project brief identified moisture-related corrosion and motor faults as concerns for equipment operating long term in an outdoor pump house. The customer therefore asked for heat tolerance, moisture and corrosion protection, and stable operation under fluctuating load.
Factor | Project requirement |
|---|---|
Application | Residential water transfer and distribution pressure support |
Operating schedule | Continuous municipal service with morning and evening peaks |
Pump house | Outdoor pump house in a hot, humid tropical climate with a long rainy season |
Operations | Straightforward operation and routine maintenance |
Selection priorities | High transfer capacity, stable pressure, low noise, heat and moisture protection, and straightforward maintenance |
Manufacturing, factory inspection, and dispatch were completed within 35 working days, followed by a 7-day sea freight transit to Hai Phong port, achieving a total project fulfillment timeline of 50 working days. The customer was a local distributor and handled on-site installation and commissioning.
The three project photographs document the vertical turbine pump installation. A crane lowered the blue pump assembly into the outdoor work area, the crew guided it into position, and installers worked at the installation point to align the equipment. Local installation and commissioning were scheduled around the municipal upgrade.
| | |
From left to right, the crane lifts the pump assembly, the crew guides it into position, and installers align equipment at the site. Photographs from the Thanh Hoa project.
The customer reported that the station ran steadily after commissioning. During peak hours, system pressure stabilized significantly, ensuring consistent water distribution across the entire service zone. The project feedback described the earlier peak-period water shortage and pressure instability as resolved and credited the upgrade with improving the reliability of household water supply.
The customer reported no observed corrosion or faults during continuous service. The IP55 motor ran continuously for two years without a reported fault. The customer also reported energy savings with variable-speed operation and found the equipment easy to operate and maintain.
The customer was satisfied with the equipment’s operating stability, its suitability for the hot and humid pump-house conditions, and the delivery service. The municipal water supply upgrade was completed.
For a municipal water supply upgrade, include peak and off-peak flow, required total head or target distribution pressure, daily operating schedule, and pump-house exposure. Existing pump curves and pressure readings during the morning and evening peaks help define where additional transfer capacity or better pressure control is needed.